I-PRESSĀ® SUGGESTED MAINTENANCE SCHEDULE
ONLY PERFORMED BY AUTHORIZED MAINTENANCE TEAM LOCK OUT - TAG OUT
DAILY
1) Prior to starting press do a complete walk around, look & listen and document anything that seems out of place.
2) No obstructions in die area.
3) Area around press is clean.
4) Point of operations guards are in place with proper function.
5) All electrical panels are closed/locked.
6) No air leaks.
7) No oil leaks.
8) No unusual electrical noises..
9) Auto grease tank level is correct.
10) ACB oil tank is full.
11) ACB pressure set up for upper die weight.
12) Turn speed to minimum before starting main motor.
13) Press start up and control test: INCH, SINGLE, CONTINUOUS, RAM STOP, TOP STOP, EMERGENCY STOP.
14) Make sure slide stops at or near TDC in INCH and SINGLE stroke mode.
WEEKLY
1) Same as daily inspection
2) Inspect air line lubrication near DSV valve and clutch and fill as needed (see lube chart for oil type).
3) Drain air tanks of any moisture and empty collection tray.
4) Check imline air filter and drain as needed.
5) Release HOLP / HYDRAULIC overload and re-presurize (see HOLP instructions).
IF YOU WOULD LIKE ANNUAL PREVENTATIVE
MAINTENANCE PROGRAMS CALL
SUTHERLAND 310-453-6981